Our Space | April 2019

 Block 81

Tiong Bahru Conservation Walk-up

Construction Sequence

Block 81 | 18th July 1955 to March 2019 |

original construction 1937

Keys acquired to Block 81 #02-65a on 14th January 2019. Reconstruction of the unit is complete. On this page, watch as we brought our new space at Block 81 to life with a sensitive restoration, befitting this historical neighbourhood. 

Construction sequence photos below.

Final move-in 23rd April 2019 

 

Go to Final Photos

 

12.11.21 | Christmas Light Up

23.04.19 | TPR-B81 Layout Plan | R4

September 21 2018 | Tiong Poh Road Block 81 02.65A > 1,216 sq ft    Existing condition 

28.01.19 | Opening up concealed air vents for restoration | pre-construction with URA permission
28.01.19 | Opening up concealed air vents for restoration | pre-construction with URA permission
28.01.19 | Opening up concealed air vents for restoration

27.02.19 | Demolition Day 1 > a column at the intersections of the beams, on the original plans does not exist. A huge portion of the original interior facade wall is missing

27.02.19 | Demolition Day 1 > Internal facade wall is brought down to structure, as the existing red brick de-bonded when the windows were removed. Better to re-build with new bricks.

27.02.19 | Demolition Day 1
27.02.19 | Demolition Day 1
27.02.19 | Demolition Day 1 > the gym area is opened up.
28.02.19 | Demolition Day 2 > the bedroom is opened up.

28.02.19 | Demolition Day 2 > the bedroom is opened up. A shaft and column indicated on the original plan, doesn't exist. Good news - the space between the bed + TV can become wider.

28.02.19 | Demolition Day 2
28.02.19 | Demolition Day 2
28.02.19 | Demolition Day 2
28.02.19 | Demolition Day 2

28.02.19 | Demolition Day 2 > a column at the intersections of the beams, on the original plans does not exist. It's a brick 'column'. Non-load bearing.

01.03.19 | Demolition Day 3
01.03.19 | Demolition Day 3 > finding the original Balcony floor set-down along the facade wall
01.03.19 | Demolition Day 3 > Balcony floor requires removal of a lot of rubble
01.03.19 | Demolition Day 3 > Balcony floor has a perimeter trench drain.
02.03.19 | Demolition Day 4 > Clean-up
02.03.19 | Demolition Day 4 > Clean-up. All the rubble removed.
02.03.19 | Demolition Day 4 > Clean-up, half of the Balcony not cleared. Bricks arrive on Friday, the 8th.
04.03.19 | Day 5 > Dismantling the ceiling planks at Penthouse One for re-location to Block 81
04.03.19 | Day 5 > Recovery of the balcony is complete | bench retained
04.03.19 | Day 5 > Screeding of the floor begins.
05.03.19 | Day 6 > Screeding needs one more day.
06.03.19 | Day 7 > Screeding complete. Electrical has started
06.03.19 | Day 7 > Screeding complete. Electrical has started

08.04.19 | Day 8 > Screeding complete. Electrical is 90% complete, cabinetry heights are set. 160 year old shop house doors are ready for relocation from the Pearlbank Penthouse next week.

08.03.19 | Day 8 > Masonry begins. The missing Balcony walls will be restored by Saturday afternoon.
08.03.19 | Day 8 > Masonry begins. The missing Balcony walls will be restored by Saturday afternoon.
12.03.19 | Day 10 > Office walls are up, A/C pipes are being run.
12.03.19 | Day 10 > plumbing is ongoing. Rigel off the floor toilet has swopped position with the shower.
12.03.19 | Day 10 > final cement rendering underway. The new wall texture will match to 1937 render
15.03.19 | Day 13 > The first ceiling plank at the living room | fibre optic cable arrives
15.03.19 | Day 13 > The office has power installed | newspapers in the vents found from the 1950's
15.03.19 | Day 13 > From Living room to Kitchen | Missing internal facade restored
15.03.19 | Day 13 > The bedroom ceiling taking shape
15.03.19 | Day 13 > Repairs to the exterior | A-C piping ready for the condenser
15.03.19 | Day 13 > Plumbing controls at the central pylon underway
16.01.19 | Day 14 > Living Room floor planks removed from the Penthouse
16.03.19 | Day 14 > OOOPS, it looks like the Town Council gave us the wrong paint color
16.03.19 | Day 14 > OOOPS, it looks like the Town Council gave us the wrong paint color
16.03.19 | Day 14 > View of the Kitchen from the Entry door, floor planks start.
16.03.19 | Day 14 > Entry + Sliding Door mock-up
16.03.19 | Day 14 > Fixed Panel mock-up
16.03.19 | Day 14 > Fixed Panel mock-up | new render gets 6 layers of paint to match 1937 walls

16.03.19 | Day 14 > Testing the paint over a repaired area of wall. Needs 6 coats of paint to blend into the old portions of wall.

20.03.19 | Day 17 > Living Room Ceiling planks
20.03.19 | Day 17 > undercoat paint
20.03.19 | Day 17 > Tile begins > finish around the toilet first, so it can be used sooner.
20.03.19 | Day 17 > Living Room flooring almost complete
20.03.19 | Day 17 > Balcony ready for tile | Stainless steel edging at bench
20.01.19 | Day 17 > Paint Color corrected.
26.01.19 | Day 22 > Master Bedroom floor planks removed from the Pearlbank Penthouse
26.01.19 | Day 22 > Office ready for carpet
26.01.19 | Day 22 > Bedroom floor is to be installed tomorrow, then bookcases next Monday
26.01.19 | Day 22 > Bathroom shower ready for grouting soon
26.01.19 | Day 22 > Living Room ceilings complete | just wipe the dust off the timber
26.01.19 | Day 22 > Sorry Tile guys, the Balcony Bench mosaic was rejected. Try again.
27.01.19 | Day 23 > Tile re-do at Balcony bench
27.01.19 | Day 23 > Cleaning ceiling planks
27.01.19 | Day 23 > Tile at Kitchen floor
27.01.19 | Day 23 > major clean-up coming this weekend
28.01.19 | Day 24 > Floors being completed | all wires and pipes run under the floors eliminating conduits
28.01.19 | Day 24 > A/C is completed > 4 units
01.04.19 | Day 27 > Balcony Bench tile installed
01.04.19 | Day 27 > Bedroom Headboard
01.04.19 | Day 27 > Tile at Balcony windows
01.04.19 | Day 27 > Bedroom bookcases arrive
01.04.19 | Day 27 > New concrete air vent installed
01.04.19 | Day 27 > Bedroom bookcases arrive
02.04.19 | Day 28 > Entry Gate
03.04.19 | Day 29 > Library underway. Ceiling planks with too much variation, need to revise.

03.04.19 | Day 29 > Grouting of Limestone at the Balcony has begun. Exciting day tomorrow [4th] - The new doors and windows arrive !

04.04.19 | Day 30 > Library underway. 100 boxes with 6,000 books arrive, all numbered for exact location
04.04.19 | Day 30 > Library is installed, before the bookcases are even finished
05.04.19 | Day 31 > Paint is dry at new upper shelf. 1,500 CD's all have a place.
08.04.19 | Day 34 > Doors are a few days late, but starting to install, then walls can be completed

08.04.19 | Day 34 > Doors are a few days late, but starting to install. OOPS, the antique ball fan is not aligned with the center of the bed. Re-do tomorrow guys. Bookcase now completed

08.04.19 | Day 34 > Plumbing controls at the Bathroom. The shower and toilet will work tomorrow ! Streamlined Modern look

Day 34 | Antique ball fan relocated from the Pearlbank Penthouse to the Balcony.
Day 34 | Artemide Catamaran relocated from the Penthouse office, now at the Boffi Kitchen Island Unit.
09.04.19 | Day 35 > Antique shophouse doors finally installed. Ready for Starhub fibre optic connection on Friday morning, 12th April.
10.04.19 | Day 36 > Carpet installed at Office
10.04.19 | Day 36 > Half the kitchen windows are in
10.04.19 | Day 36 > Living Room cabinets are complete, more boxes arrive from the penthouse
10.04.19 | Day 36 > Doors at Living room are in, walls can be completed
10.04.19 | Day 36 > Ceiling fan re-positioned
10.04.19 | Day 36 > Walk in closet to toilet
10.04.19 | Day 36 > Kitchen windows from outside, the ugly alum frames are finally removed
11.04.19 | Day 37 > Rendering the internal facade wall and we are almost there
11.04.19 | Day 37 > Windows are installed, so render can be completed

11.04.19 | Day 37 > The ugly aluminum frame windows are finally all removed, opening the balcony for the first time since 2006

11.04.19 | Day 37 > opening the balcony, the original 1937 character is being restored
11.04.19 | Day 37 > rendering moves fast now, making the spaces more complete

11.04.19 | Day 37 > office computers are shifted and the network re-connected, we are out of Pearlbank

11.04.19 | Day 37 > the kitchen rear counter is a custom construction resting on the existing bench, to match the Boffi K2 Kitchen counter from Milan.

13.04.19 | Day 39 > the Boffi K2 Kitchen unit arrives from the Penthouse at Pearlbank Apartments
13.04.19 | Day 39 > Shalom hand carries the antique mirror down 37 floors by hand
13.04.19 | Day 39 > Shalom keeping spirits up, as they descend the full height of Pearlbank Apartments
15.04.19 | Day 41 > All the big items are in, time to close up the kitchen
17.04.19 | Day 43 > Mosaic Tile continues in the bathroom
17.04.19 | Day 43 > Florim Casamood | Neutra 6.0 Verto Lux | 01 White Mosaico C > $45 sgd sq ft

17.04.19 | Day 43 > No longer living at Pearlbank Apartments, but the rush is on to clear everything out and hand over the flat to Capitaland

20.04.19 | Day 46 > Shalom lifts the sofa onto the balcony

20.04.19 | Day 46 > Shalom lifts the sofa through the kitchen, as all entryway openings to public corridors in Tiong Bahru are 27 inch wide. The new Kitchen door is 32 inches wide.

20.04.19 | Day 46 > The final move goes quickly, as most items are in the living room. 6 moves in all
 